The DrawToBid manualSearch the manual

Chapter 20

Where the money sits

Chapter 5 opened the cost estimate and read the tab you land on. It listed the other seven and gave three of them a single line each. This chapter is those three: By party, Details and Equipment.

They are three ways of looking at the same money. By party splits the job by who is doing the work. Details lays the same job out work by work, for reading. Equipment is the machine time the works call for. Nothing in any of them is typed in by you except one figure on Equipment — they are otherwise all views of what your building costs.

Everything here was read on a real job — a timber-framed house with one subcontractor on the foundations — in one sitting on 6 September 2026, so you can follow the arithmetic rather than take it on trust. Read the arithmetic, not the amounts; your own job will carry its own.

One note on the name at the top of the panel. It is headed Cost estimate and then the name of the building the estimate is of, because a project can hold more than one. A subcontractor's banner names the job instead. Both are the same job here, and the figures below all come from it.


Who can see these three

Before anything else, because it is the shortest way to understand what these tabs are for.

you, the company owner

where signing in puts them

your own project

tabs on the estimate

eight

can they open By party, Details or Equipment?

all three

a foreman in your company

where signing in puts them

a project of your company, read-only

tabs on the estimate

two — Total and Labor

can they open By party, Details or Equipment?

none of the three

a subcontractor on your job

where signing in puts them

your job, in a lens of their own

tabs on the estimate

seven, over their own works only

can they open By party, Details or Equipment?

all three

the customer

where signing in puts them

your job, in a lens of their own

tabs on the estimate

four — Total, Progress billing, Labor, Materials

can they open By party, Details or Equipment?

none of the three

a worker

where signing in puts them

an empty scene of their own — not your job

tabs on the estimate

five, on that empty scene

can they open By party, Details or Equipment?

not on your job at all

Read that table twice, because it is the single most useful fact in this chapter. These three tabs are the general contractor's own reckoning of their own work. They are not part of what your customer sees and not part of what your foreman sees. Nothing you do on them crosses to anybody.

(The counts are tabs. Every seat's strip also carries a right-aligned Settings, which is not one of them.)

The subcontractor is the exception, and not really an exception: they get the same three tabs over their own scope. Their panel is headed "Your works on" the job, with a banner reading Acting as their company, and every figure on it is their own cost of their own works — on this job COST $4,551.81, SUBCONTRACTOR PRICE $6,196.54, MARGIN 26.54%. They cannot see yours, and the figures reconcile inside their own scope: $3,289.45 of labour plus $1,262.36 of equipment is their $4,551.81 of cost, and that plus $1,644.73 of overhead is their $6,196.54 price. The tab they do not get is Subcontractors — they are not subcontracting anything.

The customer's four tabs carry no money at all until you send them a price. Swept for anything money-shaped on the day this chapter was driven, the customer's whole estimate held zero figures, and in their place one sentence: "Your contractor has not sent a price yet. When it arrives, you will be asked to approve it here." Chapter 8 is the road that sends it.

A foreman gets two tabs, and none of this chapter's three. He opens your project read-only — "Only the owner of a project can edit it — you have read-only access." — and the panel he gets is headed cost detail hidden.

His Total tab carries one figure, and it is not your client price. It is a PARTIAL TOTAL, and the product says underneath it exactly what is missing from it:

PARTIAL TOTAL $210,655.50

Not the client price — labor is not priced on this seat and no markup or tax layer is applied, so this total is short by both.

So the figure he can quote you is materials and machine time at cost, with no labour, no overhead and no markup in it — smaller than your cost and much smaller than your price. Your markup and your client price stay yours; chapter 7 is where that boundary is set.

A worker does not reach your job this way at all. Sign in as one and you land on an empty scene of your own; the five tabs above belong to that empty scene and every figure on them is $0. A worker reaches the job through the invitation you send, and what that seat carries is chapter 21.

Typing the project's address is not a way in, and the product says so plainly. A subcontractor, a customer and a worker who type your project's own address each get the same card — "That link didn't open. You don't have access to that project. This is your own editor." — and are put in an empty scene. The subcontractor and the customer reach your job perfectly well; they reach it by signing in, which lands them straight on it in a lens of their own. Do not send anyone the address out of your own address bar.


By party — where the money actually sits

Press BY PARTY in the tab strip.

The page is headed BY RESPONSIBILITY PARTY, and directly under that heading is one figure with a long label:

BILLABLE COST BASE (COMPANY + SUBCONTRACTORS) $287,487.45

Markup and tax are added on the Total tab.

That number is the whole job's cost before you add anything on top of it. It is the same $287,487.45 the Total tab prints as COST. If you have both tabs open in your head, they agree exactly.

Below it, one card per party. On this job there are three.

Your own company

Company — $279,487.45 Labor $76,831.95 Materials $202,173.06 ⚠ 76 of 78 materials not priced yet · 97% Price them → Equipment $482.44 Wind barrier membrane (vapour-open) — 4,278.919 SF — $85,578.39 Smart vapor retarder, Class II (variable-perm) — 3,886.489 SF — $116,594.67

This is the work you are doing yourself, split into what you pay people, what you pay for material and what you pay for machine time. The three lines add to the card's own total, exactly:

$76,831.95 + $202,173.06 + $482.44 = $279,487.45

At the foot of the card — under the Equipment line, not under the warning — it lists the material money it does have. Those two materials add to $202,173.06, the whole Materials line. The Materials subtotal on this card is made entirely of the materials you have priced. The other seventy-six contribute nothing, because DrawToBid ships no prices and will not invent one. That is what the warning line is telling you, and this card is the place it lands hardest: your materials subtotal looks like a real number and it is a number for two materials out of seventy-eight.

The unpriced count on this card is not the one on the Total tab, and neither is wrong. The Total tab counts every material in the estimate — 93 of 95 — while this card counts only the ones that are yours to buy: 76 of 78. The difference is the scope, not the arithmetic.

Press the warning line itself — it has an arrow on its left — and the card unfolds into every material on it, the priced and the unpriced together, each with its quantity and either its money or the words Not priced:

Press it again to fold them away. This is the fastest way to see what is missing rather than just how many. Seventy-eight lines open on this card, so expect to scroll.

Each subcontractor

[the subcontractor] — $8,000 Bought-in (labor + their materials) — $8,000 ~~…~~ — in bought-in (one struck-out line per material their works need — five here)

One card per subcontractor, and the whole of their scope is a single figure: the price you agreed with them. Their labour and their materials are inside it. You are not paying for their rebar separately, so the materials their works need are listed with a line through them and the words in bought-in — shown so you know they are accounted for, struck out so you do not count them twice.

This card has no unpriced-material warning and no Price them link, and that is right: none of those materials is yours to price. What you owe is the agreed figure.

Customer-supplied — NOT BILLED

Customer-supplied NOT BILLED $0 ⚠ 6 of 6 materials not priced yet · 100%

The last card is the material the customer is buying themselves. The chip says NOT BILLED and it means exactly what it says: you do not charge for these, and they are not in the billable cost base above. Six materials on this job are the customer's to buy.

Its total reads $0, and here is the thing to understand about that zero: it does not mean the customer is buying nothing. It means nothing they are buying has a price on it yet — the warning line directly under it says 6 of 6. When the customer enters what they paid (chapter 15 is their side of that), the figure fills in. Until then this card is a list, not a sum.

This card's warning line opens too, exactly as the Company card's does — the same arrow, the same press — and it names all six materials with their quantities:

This block agrees with what the customer sees. Chapter 15 describes the customer pricing the materials they supply from their own Materials tab. This is where those materials land on your side — outside your cost base, outside your bill, visible so you know they exist.

The cards add up

Yes, exactly:

Company

$279,487.45

[the subcontractor]

$8,000.00

Customer-supplied (not billed)

$0.00

the three cards added together

$287,487.45

the BILLABLE COST BASE at the top of the tab

$287,487.45

COST on the Total tab

$287,487.45

Nothing sits outside these blocks. Every dollar of the job's cost is on one of these cards.

What is not on this tab is everything you add on top: markup, overhead and tax. The tab says so itself in one line — "Markup and tax are added on the Total tab" — which is why the Total tab's client price of $302,900.41 is bigger than anything you can find here. By party is your cost. It is not your price.

Price them →

The Price them → link on the Company card takes you to the Materials tab and puts the unpriced block in front of you: a heading reading UNPRICED, the count — 93 of 95 lines · 98% — and a Show control beside it. You land on the tab already scrolled to it.

From there, pricing is the Materials tab's job, which chapter 5 points at. The link is only on the Company card — the other two cards hold no material that is yours to price.


Details — the estimate laid out for reading

Press DETAILS.

Five columns:

№

what it holds

the line number, counted straight down the tab

NAME, UNIT OF MEASURE

what it holds

the work's name, and underneath it the unit its rate is quoted in — (1 SF), (1 CY)

QUANTITY

what it holds

how much of that work the building needs

COSTS PER UNIT

what it holds

the labour cost of one unit of it, at the rate the people on that work are paid

COSTS TOTAL

what it holds

the labour money on that row

The works are gathered under the phase they belong to — Foundations, Walls, Columns, Exterior finishing, Floors, Ceilings, Floor slabs, Stairs, Roof and Other — and each phase heading carries a count in brackets. The phases start closed. Press a heading to open it: the arrow at its left turns down and the works appear underneath.

Under each work, indented, are its own lines: Payment workers with the labour norm beside it (norm: 0.13 h/unit), an Overhead, tax & markup line, and a ROW TOTAL. Those four rows together are one work's block, and it is the block — not the top row — that is the unit to read.

The setting above the table

There is a row of buttons above the column headings. They are one control, not three switches — pressing one turns the others off, and one of them is always on. It is a group of modes in the sense chapter 25 describes.

It has three positions, counted on the screen: JOINED · DETAILED · + MATERIALS & EQUIPMENT. JOINED is the one in force when the tab opens.

This is the only control in the estimate with three positions. The Labor tab carries a control that looks the same and has only two — Joined and Detailed. If you have read that there are three above the work table and found two, you were on Labor. Chapter 35 walks that tab.

Here is the same work under each of them. The work is Timber-frame structural wall (timber-frame house), quoted in square feet, and the building has six walls of that kind.

Under JOINED — one row for the work, with a ×6 chip showing it stands for six elements:

Quantity

3,361.512

Costs per unit

$3.5117383105

Payment workers (norm: 0.13 h/unit)

$11,804.79

Overhead, tax & markup (54.3%)

+$6,411.16

ROW TOTAL

$18,215.95

Under DETAILED — the same work becomes one row per wall, each under its own small heading naming the element. The first of the six:

Quantity

2,151.639

Costs per unit

$3.5117383105

Payment workers (norm: 0.13 h/unit)

$7,556

Overhead, tax & markup (54.3%)

+$4,103.64

ROW TOTAL

$11,659.64

The two rate columns multiply out, and it is worth checking one. On the DETAILED row above, 2,151.639 × $3.5117383105 = $7,556.00, and $7,556 is what the row's labour says. Then $7,556 + $4,103.64 = $11,659.64, which is the row total. Every figure in that pair of sums is the product's own, and every one of them is in the frame above.

Do not try the same multiplication on the JOINED row. A joined row's labour is the sum of the six rows it stands for, each already rounded to the penny — not the joined quantity times the rate. Multiply the joined figures and you land a few cents away from what the row says, and the gap is the rounding, not an error.

The rate is your own people's rate, not a list price, and that is the one thing worth knowing about this column. When you have assigned workers to a work, it is priced at what those workers earn, each on the share of the work he holds. A work you have assigned nobody to is priced at your company's average rate instead — which is what lets you quote a whole job before you have decided who does it. A work only half given out is half of each. So two works with the same labour norm can show different costs-per-unit figures on the same screen, and that is not an error: it is two different sets of people. Chapter 35 walks that ladder rung by rung.

So Detailed does not change the money. It changes how many rows it is spread over. That is the whole difference, and it is visible in the phase counts too. Every phase heading carries its count in brackets, and pressing DETAILED re-counts all of them at once:

Foundations

JOINED

(6)

DETAILED

(30)

Walls

JOINED

(8)

DETAILED

(152)

Columns

JOINED

(5)

DETAILED

(40)

Exterior finishing

JOINED

(1)

DETAILED

(14)

Floors

JOINED

(5)

DETAILED

(75)

Ceilings

JOINED

(4)

DETAILED

(64)

Floor slabs

JOINED

(2)

DETAILED

(4)

Stairs

JOINED

(7)

DETAILED

(7)

Roof

JOINED

(1)

DETAILED

(6)

Other

JOINED

(17)

DETAILED

(492)

Same job, one line per actual wall instead of one line per kind of wall. A phase whose count does not move — Stairs here — is one where every kind of work happens to occur on exactly one element.

Opening a work's overhead

The Overhead, tax & markup line under any work has an arrow on it.

Press it and the single line opens into the layers it is made of. On the DETAILED wall above:

Overheads

10%

$755.56

Income

20%

$1,511.13

Taxes on Labor TAX

15%

$1,133.35

Income Tax TAX

30%

$703.60

+$4,103.64

They add to the line above them exactly. The two carrying a small TAX mark are taxes; the other two are your own overhead and margin. These are the layers you set once in your company settings — chapter 14 covers setting them — and this is where you see them landing on one particular work.

The percentage on that line, 54.3%, is a percentage of the labour on that row, not of the job. Do not compare it with the percentage the Total tab shows against the whole cost; they are percentages of different things.

+ Materials & Equipment

Under + MATERIALS & EQUIPMENT the rows stay exactly as they are in Detailed — one line per actual element, and the phase counts do not move again (30, 152, 40, 14, 75, 64, 4, 7, 6, 492, the same as Detailed). What each row grows is a block of material lines underneath, each marked with a small dot. For the wall above:

MATERIALS · Mineral wool 6″ (between studs) — 2,259.224 SF — $0 / SF — $0 · Wind barrier membrane (vapour-open) — 2,603.486 SF — $20 / SF — $52,069.72 · Nails, screws & timber connectors — 92.546 lb — $0 / lb — $0 · Sealing tape (vapour barrier laps) — 482.031 LF — $0 / LF — $0 · Framing lumber SPF/DF-L #2 2×4 — 2,982.146 LF — $0 / LF — $0 · OSB 7/16″ wall sheathing — 2,366.809 SF — $0 / SF — $0 · Smart vapor retarder, Class II (variable-perm) — 2,366.809 SF — $30 / SF — $71,004.28 MATERIALS TOTAL — $123,074

This is where you see what a work actually consumes, in the quantities this building needs, with a $0 against everything you have not priced. The quantities follow the element, not the work: a smaller wall of the same kind consumes proportionally less, and you can read them side by side. The two priced lines add to the materials total exactly: $52,069.72 + $71,004.28 = $123,074.00.

Read this next part carefully, because it is the one thing on this tab that will mislead you. That wall's ROW TOTAL is still $11,659.64 while its MATERIALS TOTAL is $123,074. The two are separate figures and the row total does not include the materials. The row total is the labour plus its share of overhead and nothing else. If you read down the COSTS TOTAL column adding up row totals, you are adding up your labour bill, not your job.

The number that includes everything is COST on the Total tab, and the split of it is on By party.

Two marks on the work rows

  • Some works have a ticked box beside the name and some have an empty box with the name struck through. The struck-out ones are switched out of this estimate, and where their money would be — on the labour line and on the row total alike — the cell prints an em dash. Not $0: a zero would state a price, and a work that is switched off does not have one. Rest the pointer on the dash and it reads Excluded from estimate — not paid. Untick a work and it stops counting; its quantity stays, because the wall is still that size.

  • Works whose material you can choose carry a MATERIAL chip with the chosen material named and a Change link beside it. Chapter 30 is that window.

Printing and export

Nothing on this panel prints. There is no print button, no export, no PDF and no spreadsheet anywhere on the estimate — chapter 5 says the same about the Total tab, and it is true here too. The only way to put these numbers in front of somebody outside DrawToBid is the share link in chapter 6.

If you are thinking of handing this tab to somebody, two things are missing from it besides the printing. It does not say who is doing each work — there is no performer or assignment column on Details, and you would go to Labor for that. And its row total is not the work's cost, for the reason above.


Equipment — the machine time

Press EQUIPMENT.

Six columns on your own seat:

№ · NAME, UNIT OF MEASURE · QUANTITY · RATE · NET · PROVIDED BY

On this job, from your seat as the general contractor, the tab carries one group — Equipment (3) — with a Set all… control beside it and $482.44 against the heading. The group starts closed, like a phase on Details.

Open it and there are three rows:

1

Name, unit of measure

Backhoe excavator 0.25 m³ — m-h

Quantity

0.2

Rate

70

Net

$14

Provided by

General contractor

2

Name, unit of measure

Concrete pump truck — m-h

Quantity

0.056

Rate

70

Net

$3.92

Provided by

General contractor

3

Name, unit of measure

Mobile crane — m-h

Quantity

6.636

Rate

70

Net

$464.52

Provided by

General contractor

Name, unit of measure

Quantity

Rate

Net

TOTAL $482.44

Provided by

That is the whole mechanism of this tab, in three rows:

  • The unit is machine-hours. m-h means hours of that machine.

  • You never type the hours. They come from the work. The catalog entry for concrete pumping carries the pump-truck time the work needs, and DrawToBid multiplies it by how much pumping this building calls for.

  • You do type the rate. It sits in an editable box on each row, with a $ beside it, and Set all… above the group fills every row at once. DrawToBid ships no machine rates, exactly as it ships no material prices. Until somebody enters one, a machine has hours and no money.

  • Quantity × rate is the net. All three rows here carry $70 an hour: 0.2 × $70 = $14.00, 0.056 × $70 = $3.92 and 6.636 × $70 = $464.52. Those three add to the $482.44 on the total row and on the group heading, and to the Equipment $482.44 line on the Company card of By party.

  • There is no tax column here, and no gross. This company levies no tax on machine time, so the tab prints only what it has: NET is the last money column, and there is no second figure beside it that has to reconcile with it. Where a company's tax settings are kept is chapter 14; this chapter does not show the tab with one configured.

A machine on somebody else's scope does not appear here at all. The foundations on this job are subcontracted, and whatever machine time that scope needs is inside the $8,000 bought-in figure on the subcontractor's card — one lump, not itemised. You cannot see from your own estimate what your subcontractor's machine time costs them, and you are not meant to: you agreed a price for the scope. The PROVIDED BY column is where that shows: every row on this job reads General contractor, because every machine on it is the company's own.

So what fills your Equipment tab?

A machine on a work you are doing yourself. Excavation, concrete pumping, crane work, floor grinding and floor sanding are the works in the catalog that call for one. Put any of them in your own scope rather than a subcontractor's and the row appears here, with its hours already worked out, waiting for you to put a rate against it.

When none of them is yours, the tab says No equipment in this estimate., your Total tab has no Equipment line and none of your By party cards has an Equipment row. On this job three of them are yours, so all three of those places carry the same $482.44.


What to remember

  • By party is your cost, split by who is doing the work. Its cards add up to the estimate's COST exactly, and nothing sits outside them. Markup and tax are not on it.

  • Every card's unpriced warning opens. Press the arrow and the card lists the materials behind the count, each with its quantity — on the Company card and on the Customer-supplied card alike. Only the Company card also offers Price them →, because only its materials are yours to price.

  • A subcontractor is one figure — the price you agreed. Their materials are shown struck out so you do not count them twice.

  • Customer-supplied is NOT BILLED and sits outside your cost base entirely. A $0 there means nothing has been priced, not that nothing is being bought.

  • Details' row total is labour plus overhead, not the work's cost. Joined and Detailed hold the same money over a different number of rows; + Materials & Equipment adds the materials underneath without adding them to the row total.

  • The view control above the Details table has three positions. The one on Labor has two.

  • Equipment shows the machine time on works you do yourself. The hours come from the work, the rate comes from you, and a machine inside a subcontractor's scope shows up on their tab, not yours.

  • A foreman's figure is not your figure. He sees a partial total with no labour, no overhead and no markup in it, and the product tells him so on the same screen.

DrawToBid records how it is used.

We send usage data to Amplitude, our analytics supplier, to make the product better and to test which page explains it best, and a report to Better Stack, our error-tracking supplier, when a page breaks or stops answering, so we can fix it. We also record the domain name of the site you came from, such as google.com or reddit.com, never the page address or the search words. Never the contents of your work, and we never sell it. Cookie details

You can turn this off in .