Chapter 18 took a work up the ladder to authorised for billing. This chapter is what turns that into money you can ask for.

Three things have to line up before DrawToBid will let you bill anything, and they are not interchangeable:

  1. The customer has agreed a price. Not a link you sent them, not a number in an email — an approval they gave inside DrawToBid, which locks.

  2. The work has climbed all the way up the ladder, to authorised for billing — chapter 18 is that road.

  3. The month being billed has ended.

Miss any one and the billing screen refuses you, and — to DrawToBid's credit — it tells you which one you missed in plain words rather than greying a button out. Most of this chapter is those three gates, in the order you meet them.

Everything below was driven on the running product on 4 September 2026, in the order it is written: the price sent, the customer signed in and approved it, and the first application composed.


The price has to be agreed first

Open the project, press Calculate, and stay on the Total tab. Underneath the figures is a panel called CUSTOMER APPROVAL:

Customer approval Send the client price to your customer their email for sign-off. Once approved it is locked. DRAFT $302,900.41

That is the whole idea in two lines. What you send is the client price — the figure the estimate already showed you — and once the customer says yes, it stops being editable.

What you are also asking them to approve

Under the price the panel carries a second block, and it is the part worth reading before you press anything:

WHAT YOU ALSO APPROVE 1 allowance in this price This rate can change until the first payment application. Smart vapor retarder, Class II (variable-perm) — ALLOWANCE — Material NOW IN THE ESTIMATE $116,594.67 · ~3,886.489 SF · $30/SF

An allowance is a line you have priced provisionally because nobody yet knows the real number. DrawToBid refuses to let one travel silently: it counts them, names them, warns on the same screen that the rate is still moveable — and says exactly when it stops being moveable, which is the first payment application, the subject of the rest of this chapter.

Send it

Request approval, at the bottom of the panel. There is no confirmation step and no dialog.

The panel changes state immediately:

PENDING APPROVAL $302,900.41

and the control where Request approval was is now Withdraw request. Beside it, a History link keeps the record of what was sent and when.

While it sits there, the price is out of your hands — which is the point of sending it.


What the customer does

The customer signs in and lands on your job, in a lens of their own, under a banner that states what the seat is for:

Customer access — set the price of the materials you supply and approve each draw. Everything else is read only.

They get four tabs where you have eight: Total, Progress billing, Labor and Materials. There is no By party, no Subcontractors, no Details and no Equipment — your trade breakdown and your subcontracting are not their business. Chapter 20 has that table in full.

The approval screen

On their Total tab, the customer gets the request as a panel of its own:

APPROVE FINAL PRICE The general contractor sent this final price for your approval. PENDING YOUR APPROVAL $302,900.41 Sent for your approval on Sep 4, 2026.

The allowance disclosure you saw travels with it, and on their side it carries a figure:

WHAT YOU ALSO APPROVE 1 allowance in this price Smart vapor retarder, Class II (variable-perm) — ALLOWANCE — Material — $89,478.36

Underneath, DrawToBid answers the question a customer actually has, and answers it honestly rather than flatteringly:

Your total cost if you approve this price — Not yet known the proposed price plus what you buy yourself

The price you asked them to approve is your price. If the customer is buying some of the materials themselves, their real outlay is your figure plus theirs, and DrawToBid will not pretend to know that total until they have filled their side in.

They have two controls: Approve and Reject.

After they approve

The panel restates itself, and the wording is the tell:

APPROVED $302,900.41 1 allowance approved on Sep 4, 2026

Three new links appear where the buttons were — View what you approved, What you signed and Compare with today. From this point the approved figure is a fixed reference: the project can carry on changing, and what you signed still says what it said.

An approval is permanent. Nothing on either seat undoes it.


Progress billing

The estimate's money tab is called PROGRESS BILLING. It is where authorised work becomes a document you send.

What it refuses, and why that is useful

Before the price was agreed, this tab held no controls at all — only an explanation:

You cannot compose an application yet The final price has not been sent to the customer for approval yet. Send it for approval — an application is a breakdown of the figure the customer approved.

That sentence is the model of this whole screen. An application is not a bill you write; it is a breakdown of an agreed number. Everything the tab does follows from that, including refusing to exist before the number is agreed.

The refusal changes its reason on its own

Send the price for approval and come back to this tab. You have pressed nothing here, and the heading still reads You cannot compose an application yet — but the sentence under it is a different sentence:

You cannot compose an application yet The final price is with the customer and has not been approved yet. An application bills against the approved figure, so this waits on them.

The tab is telling you whose move it is. Before, the missing step was yours and it named it — Send it for approval. Now the step belongs to the customer, and the tab says so rather than repeating an instruction you have already carried out.

Once the customer approves, the refusal is gone:

No applications yet. Bill the first period when you're ready.

with a + New application button.

Composing one

+ New application opens a short form. It asks for nothing — there is no period to choose, no lines to tick, no amount to type. It simply states what it is about to do:

Application No. 1 · Aug 2026 This application will report the state of the work as of Aug 31, 2026.

Everything you authorised as payable by that date is on this application — no matter when you authorised it. Anything you authorise later goes on the next application.

Every percentage is read from the scene.

Three things to take from that.

Applications are monthly, numbered, and consecutive. Not "an invoice when I feel like it" — Application No. 1, covering a named calendar month, and the ones after it follow in order.

The cut-off is a date, not the moment you press. What lands on the application is everything authorised by the end of that month, whenever you happened to authorise it. Authorise something late and it does not fall through a crack; it goes on the next one.

You type no figures. Every percentage is read from the work itself — from the rung you authorised — which is why the whole ladder in chapter 18 had to be climbed before this screen was any use.

The form has two controls: Cancel and Create application.

What came back

Pressing Create application produced a real document, and an empty one:

TO YOUR CUSTOMER · USD No work was completed in Aug 2026, so there is no application for it. It has been recorded, and needs no signature. The next application covers Sep 2026. You can create it from Oct 1, 2026, once the month has ended.

Application No. 1 · Aug 2026 — No work this month

That is correct behaviour, and it is worth understanding rather than being surprised by:

  • the work on this project was authorised in September, and this application covers August, so genuinely nothing had been authorised by August 31st;

  • DrawToBid still creates the August application and records it — "recorded so every month stays covered" — so the numbering never has a hole in it;

  • and it has no send control, because there is nothing to send. Counted on the finished document: the tab carries a rail, a row, a state pill and the no-work sentence, and no Send, no Print and no Discard.

And the door closes behind it. With August composed, + New application is gone and the tab says why in the same breath:


Where this chapter stops

A payment application with work and money on it still could not be produced, and the reason is a calendar rather than a fault.

An application covers a calendar month that has ended, and it carries the work authorised by the last day of that month. On 4 September 2026 the whole road in front of it was walked for the first time — the price sent, approved by the customer, the tab unlocked, the first application composed — and it came out empty, because the work on this job was authorised in September and the only month available to bill was August.

The next one covers September and cannot be created before 1 October 2026. The product says so itself, in the sentence above.

So the parts of this screen a reader most needs — what a populated application looks like, what sending it does, what the customer sees when it arrives, and what happens when they accept it — have still not been seen, and this manual does not describe screens nobody has looked at.

What is new since the last edition, and it is most of the chapter: the three gates are no longer described, they are driven. The price was sent and its state watched change; the customer's own screen was opened and the approval given from it; the refusal was read in both of its forms; the compose form was opened and pressed; and the empty document it produced is quoted word for word, including the date it names for the next one.


What this chapter did not cover

Named so their absence is not read as everything being covered:

  • a populated payment application — sending it, the customer receiving it, acceptance, and what a second application does about what the first already billed;

  • rejecting a price rather than approving it, and what re-approval looks like after the scope changes;

  • withdrawing a request once it has been sent;

  • the subcontractor's own applications, which he composes against you exactly as you compose against the customer.

DrawToBid records how it is used.

We send usage data to Amplitude, our analytics supplier, to make the product better and to test which page explains it best, and a report to Better Stack, our error-tracking supplier, when a page breaks or stops answering, so we can fix it. We also record the domain name of the site you came from, such as google.com or reddit.com, never the page address or the search words. Never the contents of your work, and we never sell it. Cookie details

You can turn this off in .