Chapter 13

Put the work out to tender

Chapter 7 handed work to your own people. Chapter 9 turned the table around and sat you in the subcontractor's chair. This chapter is about the decision in between: you have an estimate, you want somebody else to do part of it, and you want more than one company to price it before you choose.

That is a tender, and DrawToBid runs it inside the estimate you already have. There is no separate tender page, no bid inbox, no document to write. You take a work off your own estimate, name the companies who may price it, and they answer with a number.

Everything below was carried out on the running product, in the order it is written, and every picture is a frame from that walk.


Before you can tender

A tender is offered to companies that are already on the project. You cannot type a stranger's email into a tender; the list of possible bidders is built from companies you have invited and who have accepted.

The subcontractors registry

That invitation is sent from your company, not from the estimate. Open your company and go to Projects › Subcontractors. The first control on the page is the one everything else depends on — the project this invitation is for:

Subcontractors

Invite subs to a project and track where each one stands. Every invite is for the selected project only.

PROJECT — DrawToBid funny home

Invite a subcontractor — Invite one company to work on this project as a subcontractor. Every invite is for the selected project only.

Invited to this project — Pending until they accept; then their lifecycle, price and scope show here.

Pick the project at the top first — the invitation is bound to it. On a project that has never had a subcontractor the list underneath says so in as many words ("No subcontractors on this project yet. Invite one above and it appears here right away as a pending invite, then updates as they accept."). The project this chapter was walked on already had one, so what the list shows is a company already at work:

[the subcontractor] — Accepted · OFFERED · ≈ $8,000 PROVISIONAL · 3 works ↗ · Archive

[the subcontractor] still has 3 works on DrawToBid funny home. Withdraw the subcontract in the estimate first — then you can archive them here.

That row is the whole registry in miniature: who is on the project, where they have got to, what they are being paid, how much of the job they hold, and the one thing you can do about it. Chapter 16 is where the Withdraw road in that sentence goes.

Inviting a company

To invite a company, type its name into the search box:

The search offers companies as you type:

Choose it, and the form says plainly what it is about to do:

ⓘ This invite is for DrawToBid funny home only. Another project needs its own invite.

Press the invite button and you get "Invitation sent to Nimbus Roofing Co."

Do it again for the second company. Both then appear in the list underneath, each reading Pending, with a dash where the price and the lifecycle will go and 0 works:

Two companies were invited this way for this chapter. You can invite more; the tender screens do not have a limit.

The invitation they receive

The invited company sees it under Projects › Invitations in their own company — this is Chapter 9's screen:

Invitations — Projects other companies invited you to work on. Accept a pending invite to open the project; past invitations stay here for your records.

Pending — Awaiting your response.

DrawToBid funny home · by [your company] · Subcontractor · Sep 4, 2026

Pending — Accept & open · Decline

Nothing on that row says the word "tender". The invitation you send is an ordinary invitation to work on the project. A company must accept before it can be asked to bid, so on the road this chapter walks the invitation always arrives first, with no tender on it to mention.

The ⚖ Tender marker belongs to the rows further down the page. Once a company has accepted and has works out to bid to it, its row in History carries the scales — the losing bidder's row, at the end of this chapter, is one you will see it on. It is a mark on a company you are already in a tender with, not on an invitation that has yet to be answered.

Accepting it

Press Accept & open and you are taken straight into the project:

Afterwards the row leaves Pending — which then reads "No pending invitations — you're all caught up." — and appears under History as Accepted, with an Open project ↗ link:

Acceptance comes first

They must accept before you can tender to them. Until they do, they are not offered as bidders at all — not greyed out, not "awaiting acceptance"; they are simply not in the list. So if a company you invited is missing from the bidder list, the answer is almost always that they have not opened the project yet. Chapter 9 explains what accepting involves on their side — in short, opening the project is accepting it.


Opening a tender

Open the project, press Calculate, and go to the Labor tab. This is the same table Chapter 7 used to put work on your own people, and the tender lives in the same control.

Assign, then Tender

Find the work you want somebody else to do and press Assign… in its Assignee column:

The panel that opens has two modes along the top:

Assign — Reinforced concrete pad foundations

[ Split ] [ Tender ]

Split is Chapter 7 — give the work to your own worker, crew or a subcontractor you have already settled with. Tender is this chapter. Press it and the panel changes completely:

BIDDERS — ACCEPTED SUBCONTRACTORS ON THIS PROJECT

☐ [the subcontractor] — bidding — 100% ☐ Nimbus Roofing Co — bidding — 100% ☐ Cascade Framing Co — bidding — 100%

Each selected company gets the whole work at 100% to bid its own price. Bids don't enter the estimate until you award one.

Put out to tender (0)

What every bidder is asked

Read that middle sentence carefully, because it is the whole shape of the feature:

  • Each company is asked for the whole work. A tender is not split between bidders the way an assignment can be split between two of your workers. Everyone prices 100% of it, and there is no share box in this mode at all.

  • Nothing enters your estimate. A tender costs you nothing and changes no total. Your estimate is exactly what it was.

Committing the tender

The list is every accepted subcontractor on the project, not only the ones you had this tender in mind for. A company already doing work for you here — [the subcontractor] above — is offered as a bidder like any other. Ticking is how you choose; the button counts what you have ticked, and stays dead until you tick something:

Press it. The panel closes and the work's assignee cell now reads:

⚖ Under tender — 2 bids

Two things that catch people out

Nothing is sent until you save

Nothing has reached the other companies until you save. Putting a work out to tender is an edit to your estimate like any other, and the estimate holds your edits until you press Save changes in the header. The row says Under tender immediately; the bidders see nothing at all until the save goes through. If you close the estimate without saving, no tender was ever sent.

One tender, not two

Tendering a second work to the same companies does not create a second tender. It grows the first one. Two works were put out to the same two companies here, and each company then had one bid to give, covering both works. They cannot price one and decline the other, and you cannot award one of them and leave the other open. The package is the unit — which is why the second work's cell reads "Under tender — 2 bids" and not "4 bids".

The estimate has not moved

While the tender is open and nobody has bid, the estimate is untouched. The Total tab read COST $287,332.90 · CLIENT PRICE $302,669.95 · MARGIN 5.07% before the tender and the same figures after it, to the cent, with no line of any kind for the companies bidding:


What the bidders do

Their side is Chapter 9's chapter, so this is the short version — enough to know what you are waiting for.

The tender bid strip

The invited company opens the project and presses Calculate, and on its Total tab, in the place where Chapter 9's ordinary quote strip sits, it finds this instead:

YOUR TENDER BID

Enter your bid for this tender. You can revise until they award it.

DRAFT $172.61

Submit bid · History

The figure that starts there is their own computed cost of the tendered works, worked out from their own rates and quantities — not yours, and not a number you gave them. In this walk it was $172.61, which is what the two works came to on that company's books before it had priced anything.

Where the bid is typed

The bid is not typed into that strip. There is no box in it — the figure is text. The bid is typed into the Subcontractor price field further up the same Total tab, which is the single place a company's own price is set anywhere in DrawToBid:

Submitting and revising

Type a figure there and leave the field, and the strip below picks it up at once — no save is needed, the field writes as you leave it. Then press Submit bid, which sends exactly what the strip is showing:

Once sent, their strip reads SUBMITTED with the same amount, and the control becomes Revise bid — so a company can take its bid back and re-price it right up until you award:

No closing date

No control on either side sets a closing date. A tender stays open until you do something with it, and if you never do, it stays open.


Reading the bids

Where the bids live

The bids do not appear on the Labor tab where you started. Opening the tender control on a tendered work still shows the companies that may bid and the Put out to tender button, and adds a signpost above them pointing at the tab where the bids are read:

Review & award on the Subcontractors tab →

The bid cards

So go to the Subcontractors tab of the estimate. At the top of it:

BIDS UNDER REVIEW · 2

Award a subcontractor to give them their whole tendered scope. The other bidders on those works are closed.

and one card per bidding company:

Nimbus Roofing Co SUBMITTED 2 works ↗ $41,000 [ Award ]

Lowest submitted bid: Nimbus Roofing Co — $41,000.

Cascade Framing Co SUBMITTED 2 works ↗ $47,500 [ Award ]

That is the comparison. It is worth being precise about what is on it, because a builder used to a bid tab in a spreadsheet will expect more.

What each card tells you

the company name

what it is

who is offering

SUBMITTED

what it is

they have sent a price

N works ↗

what it is

how many works their bid covers — press it

the amount

what it is

the whole price for that whole package

Award

what it is

give them the lot

Both companies in this walk answered, so what a card looks like while a company has been asked and has not yet priced it was not seen.

The scope behind the count

The work count on a card is a control — press it:

It opens the scope behind the number, and on the general contractor's side it names the works:

Works in Nimbus Roofing Co's tender

2 works put out to bid to this subcontractor.

Reinforced concrete pad foundations Excavation for pad foundations

Close

The lowest bid

And underneath the cheapest card, the product does the arithmetic you would otherwise do yourself:

Lowest submitted bid: Nimbus Roofing Co — $41,000.

What the cards leave out

This matters more than the list above, because these are the things you will have to find out another way:

  • Nothing but a price. No hours, no crew size, no start date, no finish date, no note from the bidder — and nothing on the bidder's own screen to write one with. Their whole bidding surface is a price box on the Total tab, a Submit bid button and a History link. There is nowhere for a company to say "that price assumes you have the site cleared", and nowhere on this card to ask.

  • No breakdown. One number covers the whole package. You cannot see what the company put on the concrete and what it put on the excavation, and you cannot award one work of the two.

  • Nothing about the company. No trade, no size, no other jobs, no history of what they bid or won before. If you have used them before, the card does not say so.

  • No comparison against doing it yourself. Your own estimate says what those works cost you to self-perform, but the bid card does not put the two side by side. You have to hold your own figure in your head — or read it off the Labor tab in another tab of the same screen.

  • How the card prints cents was not exercised. Both bids on this walk were whole dollars — $41,000 and $47,500 — so this chapter does not say what a bid with cents in it looks like.

The estimate has still not moved

And your estimate still has not moved. With both offers sitting on the table — $41,000 and $47,500 — the Total tab read COST $287,332.90, exactly as it had before either company was asked, and carried no line for either of them. A bid is an offer, not a commitment, and DrawToBid treats it as one.


Awarding the work

The confirmation dialog

Press Award on the card you want. Nothing happens yet — you get a confirmation that spells out every consequence, and it is the clearest screen in this whole chapter:

Award Nimbus Roofing Co's bid — 2 works?

This awards Nimbus Roofing Co's whole package of 2 works together ($41,000) and adds it to your estimate. All 2 lock at once.

Awarding will: • Lock Nimbus Roofing Co's bid ($41,000) — binding, all 2 works. • Add $41,000 to your estimate (nothing was counted before now).

These works leave other bidders: • Cascade Framing Co loses all 2 works — closed, kept as a past bid.

You can change the awarded price later with Request sum change.

Cancel · Award to Nimbus Roofing Co

The middle block is the one to read twice, because it is the only place the product tells you what your choice costs the companies you did not choose:

Press Award to … and it happens at once:

Note that this one is not held until you press Save changes — unlike opening the tender, the award is written immediately.

What the award did

Four things, all of them visible:

The winner is a subcontract

1. The winner leaves the bids section and becomes a subcontract. The BIDS UNDER REVIEW band disappears once no bids are left to judge, and in its place:

SUBCONTRACT PROGRESS — Work you've handed to subcontractors — their price, status, and progress.

Nimbus Roofing Co ✓ AWARDED Site NOT STARTED Messages $41,000

Reinforced concrete pad foundations — Not started Excavation for pad foundations — Not started … and so on …

APPROVED $41,000 Request price change · History Ask for a scope change · Withdraw works…

From here on it is an ordinary subcontract, and the rest of it belongs to Chapters 7 and 8: their progress, their messages, changing the price, taking works back. Chapter 16 walks that last one.

The work list on that card counts differently from the bid card. The bid said 2 works; the subcontract card lists sixteen rows — eight of each work, because each of those two works exists eight times in the building, once on each of eight elements. Nothing is doubled; the price is the price. The two counts are of different things: one counts works, the other counts the elements those works sit on.

The awarded card is settled and says so. It reads AWARDED at the top and APPROVED $41,000 at the bottom, with Request price change rather than an approval to give — the price is agreed and locked, and changing it is a request. If you also carry an older subcontract that was never agreed — the subcontractor in this walk — that card is the one reading NOT AGREED, with "Nothing can be billed until you approve a new price." over it. The two cards sit one above the other, and the warning belongs to the un-agreed one.

The money in your estimate

2. The money entered your estimate — exactly the awarded amount and nothing else. The Total tab gained a line naming the company:

Nimbus Roofing Co (bought-in) · lump sum · $41,000

and the grand cost went from $287,332.90 to $328,332.90 — exactly $41,000 more, not a cent either side. What the work would have cost you to do yourself is no longer counted; the bought-in price stands in its place. Read the difference, not the two totals: they are that job on the day the award was driven, and the job is drawn on daily. The $41,000 is the part that will be true on yours.

The loser is closed out

3. The losing company is closed out of those works — and kept. Its card leaves the bids band and lands in a section of its own at the top of the same tab:

CLOSED BIDS — Bidders whose tender is over. What they priced stays on the record.

Cascade Framing Co — $47,500 2 works left this bid — won by another. The tender on them is closed.

So what you paid, and what you did not pay, are both still on the screen. There is nothing to press on that card.

The row on the Labor tab

4. The awarded works change how they read on the Labor tab. Their assignee cell now says ↗ Sub: Nimbus Roofing Co and the self / sub / off switch on the row shows the winning company in the middle position, locked. That decision has been made.


After the award

The winner

Everything Chapter 9 describes starts here. Signing in as the winning company and opening the project:

  • Its quote strip now reads GENERAL CONTRACTOR APPROVAL — the tender framing is gone, because the competition is over — with APPROVED $41,000 and the control changed to Request sum change. The price is agreed and locked, and changing it is a request, not an edit.

  • Its Labor tab, which carried nothing before, is now headed "Acting as Nimbus Roofing Co · your works on DrawToBid funny home" with the scope set to My works, and lists the works it won under Foundations (2), with its own hours and payment against them.

  • A work it has won carries an Assign… control of its own, so the company can put its own people on it — Chapter 9's road exactly, from staffing through to the schedule.

The winner's own totals are its own costs, not the price it won. Its COST and SUBCONTRACTOR PRICE columns are what the two works come to on its own books, out of its own catalog and its own rates; the strip above carries the contract — $41,000. The agreed price lives on the strip. The columns and the strip are answering two different questions, and a company whose own rates and markup are not set up yet will see a small figure in the columns.

So yes: winning a tender is how a company arrives at the start of Chapter 9.

The loser

They are told, and told in two places. In their own company, under Projects › Invitations, the invitation has moved into the history list and carries the outcome:

History — Invitations you've responded to, or that were withdrawn.

DrawToBid funny home · by [your company] · Subcontractor · Sep 4, 2026 ⚖ Cascade Framing Co · 2 works ↗ · $47,500 NOT SELECTED ● Accepted

And on their own estimate — the screen they actually work in — the same answer, in their own words:

YOUR TENDER BID

NOT SELECTED

This tender was awarded to another company — your bid was not selected.

$47,500 · History

Three things about that strip are worth naming, because they are what a losing bidder needs:

  • the tender framing stays — the heading still says this was a competition;

  • the figure is a record, not a control — no Submit, no Revise, no Withdraw, because there is nothing left to offer;

  • History is still there, so the trail of what was sent and when survives the loss.

The outcome appears on both of those screens — the losing company's own estimate strip, and its Invitations page — and that is where a company that did not win reads it.


Ending a tender without an award

You do not have to award. A tender can be taken back, and the same control does it.

Discarding the bids

Open the assignee cell on a work that reads ⚖ Under tender, and press Split — the mode you are switching away from tender:

The panel asks first:

Discard 1 bids and return to shared assignment? No bids have entered the estimate, so nothing is removed from the total.

Keep tender · Discard bids

Keep tender leaves everything as it was. Discard bids ends the tender:

The work drops back to the ordinary assign panel — your workers, crews and subs, a share box and an Assign button — and the bids are gone. Not archived on this screen, not marked withdrawn; gone. The prices those companies gave you are not recoverable from here.

The sentence in that confirmation is the important part and it is true: because a bid never enters the estimate before it is awarded, discarding one takes no money out of anything.

Putting the work out again

Putting the same work out again works exactly as it did the first time — open the control, press Tender, tick the companies, commit. There is no separate "reopen"; a tender is not a thing with a state you toggle, it is bids attached to a work, and putting the work out again makes new ones. What the companies who bid the first time see after a tender is discarded was not looked at from their seats, so this chapter does not say.

Who may still bid after a loss

A company that lost a tender drops out of the pool for the rest of the project. After the award above, a third work was put out to tender on the same project, and the bidder list offered the subcontractor and the winning company, and nobody else. The company that lost was no longer there to be asked. Its subcontract on this project was closed when it lost, and the pool is built from open ones — so if you want a price from that company on something else, you have to invite it onto the project again.


Without a company

Every screen in this chapter belongs to a company: the registry that sends the invitation, the Invitations page that answers it, and the estimate that carries the tender. A person signed in without a company reaches none of them, and the product says so in plain words rather than pretending the page is broken.

An account registered for this walk, belonging to no company, was pointed at each door in turn.

The doors that refuse

The Subcontractors registry — where a tender's bidders are hired onto the project:

No access to this company

You don't have an active invitation to this company workspace.

Back to editor

The Invitations page — the bidder's own door in this chapter — answers with the same three lines.

The project, by the owner's address (/draw/<company>/<project>), does not refuse; it bounces you into your own editor and tells you why:

That link didn't open

You don't have access to that project. This is your own editor.

Close

The project by the invited party's address (/draw/access/<project>) is the one door that offers a way forward — it is chapter 14's access-request queue:

This page is unavailable

Request an invitation and the owning company will review it. You'll get access to this project once they approve.

Requesting as … — Add a note (optional) — Request an invitation

That is the honest route for somebody with no company who has been sent a project link: ask, and wait for the owning company to answer. Chapter 14 explains what happens to that request.

What the seat does get

What the account does get is the free editor of Chapter 36 — it lands on /draw/guest with an empty project, its cloud state reading "kept locally":

Tendering is not a feature that seat is missing a button for; it is a conversation between two companies, and it needs one of you to have a company before it can start.


What this chapter did not cover

Named so their absence is not read as everything being covered:

  • A bidder declining to bid. Every invited company here priced the work. What the general contractor sees when a company simply never answers was not exercised.

  • The bidder's own view of the scope it is pricing. This chapter reads the works dialog from the general contractor's seat, where it names the works. What the same dialog holds on the bidding company's seat is not described here.

  • Withdrawing an award, or what happens to a tender when you take works back off a subcontractor afterwards — chapter 16 walks the withdrawal itself.

  • A tender with three or more bidders, and what a partial loss looks like when one company wins some of the works another was also bidding on.

  • The message channel on the subcontract card, which is the only place in the product where you and a bidder could discuss a price.

  • Billing the awarded subcontract — that is Chapter 8's road, from the other side.

DrawToBid records how it is used.

We send usage data to Amplitude, our analytics supplier, to make the product better and to test which page explains it best, and a report to Better Stack, our error-tracking supplier, when a page breaks or stops answering, so we can fix it. We also record the domain name of the site you came from, such as google.com or reddit.com, never the page address or the search words. Never the contents of your work, and we never sell it. Cookie details