Chapter 10
Plan the job's time
Chapter 7 put people on the work and Chapter 9 laid one person's hours onto a calendar. Both of those are done a work at a time, from inside the estimate. This chapter is the view above them: one page that shows every person you employ, on every project, across the whole calendar.
It answers one question well, and it is a question that decides most of a builder's week:
Who is busy, who is free, and when.
It is worth being clear at the start about what it is not, because the page looks like a planner and is not one. You cannot schedule anything here. Nothing on this page writes. Read the section Nothing on this page moves anything before you go looking for a control that is not there.
Everything below was carried out on the running product, in the order it is written.
Where it is
In the company workspace, the left-hand rail has a PROJECTS section. Planning sits in it, second of five, between All projects and Subcontractors.
The page opens with the heading Planning and, under it, a line naming your company:
Occupancy across all projects for [your company]
That sentence is an accurate description of the whole page. It is about occupancy — who is taken up and who is not. It is not about tasks, deadlines, or the order work has to happen in.
What is on the screen
A single strip of controls, then a calendar, then one line of legend.
The strip carries ten controls and no others:
| control | what it does |
|---|---|
| ‹ · Today · › | move the calendar back, jump to today, move it forward |
| Timeline · Week · Day · Month · List | five ways to look at the same schedule |
| Everyone | narrow the calendar to one worker or one crew |
| All projects | narrow it to one project, or several |
‹ · Today · ›
what it does
move the calendar back, jump to today, move it forward
Timeline · Week · Day · Month · List
what it does
five ways to look at the same schedule
Everyone
what it does
narrow the calendar to one worker or one crew
All projects
what it does
narrow it to one project, or several
What the two filters hold
Opening the two filters gives you, in the first, Everyone under a heading of ALL, then every worker by name under WORKERS, then every crew under CREWS — fourteen and two respectively on the company walked here. The second lists All projects under PROJECTS followed by each of the company's projects by name.
The read-out and the now line
Beside the arrows is a period read-out. Under the calendar is a legend with a small accent-coloured tick:
The accent line marks the current time (now).
That accent line is drawn vertically down the calendar wherever "now" falls, so you can see at a glance what is behind you and what is ahead.
The page opens on today
Every view opens on the current day. If the work on your jobs is not happening this week, the first thing you see is an empty calendar — lanes with your people's names down the side and nothing in them.
That is not a fault and it is not a page that failed to load. It means nothing is scheduled today. Press ‹ or switch to Month and the work appears where it actually sits.
This is exactly what happened on the walk, and it is worth knowing before you conclude the page is broken: opened on 4 September, all five views came up carrying no bars at all, while one press of ‹ in Month view reached August and its sixteen. On a job whose schedule was laid a few weeks ago, the page can open completely blank and be perfectly correct.
Only dated work is on this page
This is the second thing that surprises people, and it matters more than the first.
A work can be assigned to somebody without ever being scheduled. Chapter 7 assigns; the dates are a separate act. On the estimate, a holder who has no dates yet reads:
Assigned · Not scheduled
Work in that state is not on the Planning page at all. Not as a marker, not in a tray, not in a list of things needing dates. It is simply absent.
On the project walked for this chapter, ten holders were assigned across the job and only two of them had dates. The Planning page showed those two and nothing else — the other eight were nowhere on it.
So read the page for what it is: a picture of the time that has been committed, not a checklist of the work that still needs committing. To find what has no dates, go to the estimate and look for the Assigned · Not scheduled lines.
Nothing on this page moves anything
The calendar is read-only, deliberately and completely.
There is no input field of any kind on the page. Counted on the running page: zero input or text boxes anywhere on it.
There is no Save, no Set dates, no Auto-schedule, no Add.
The bars cannot be dragged. Taking hold of one and pulling it sideways across the calendar leaves it exactly where it was.
The ten controls above are the whole page. Every one of them changes what you are looking at, and none of them changes the plan.
Clicking a bar opens a small panel about that bar, and that panel is read-only too — counted the same way, it carries no input of any kind either.
Dates are set where the work is, not here — on the holder's line in the estimate, which is the next section.
How a date gets onto a work
You do this in the estimate, not on this page.
Open the project, open the cost estimate, and go to the Labor tab. Work is grouped by category and the groups start collapsed — all ten of them on the job walked here — so expand the one you want.
Narrow to one person first
Narrow the tab to one person first if the job is a busy one. The FILTER row carries an assignee picker offering Any assignee, Unassigned, and every worker on the roster by name and trade — nineteen entries here. It is worth pressing before you expand anything: on a job with a full roster, opening every category at once puts every holder line on the screen and the table takes a long moment to settle.
A holder's line
Each work row can be opened to show the people holding it. A holder's line carries the trade, the hours, the share, an Unassign, where the work stands, a Take up control — and the dates, or the words Assigned · Not scheduled if they have none. Read on one work, narrowed to one man, the four lines were:
Jake Thompson (carpenter) · 65.6 h · 15% of this work — Assigned · Not scheduled Luis Ortega (concrete worker) · 131.2 h · 30% of this work — Assigned · Not scheduled Frank Adams (general builder) · 109.3 h · 25% of this work — from Jul 20 to Aug 4 Billy Green (laborer) · 131.2 h · 30% of this work — from Jul 20 to Aug 6
Two with dates and two without, on one work — which is exactly the split the section above is about: the first two are nowhere on the Planning page, and the last two are the bars you see there.
The dates are a button
The dates are a button. On a line with none, the button's own words are Assigned · Not scheduled; on a line that has them, it is the span. Press it and a scheduling surface opens for that one person on that one work.
Schedule assignment Jake Thompson (carpenter) · Timber-frame structural wall 65.6h to schedule — your 15% share of 437.3h ≈ 8 slots of 8h + 1 short slot ~1.6h
The arithmetic is already done
DrawToBid has already done the arithmetic before you place anything: it knows the person's share of the work, turns that share into hours, and tells you how many working days that comes to. On this line 15% of a 437.3-hour work is 65.6 hours, and 65.6 hours is eight full days and a short one.
The week calendar
Under that is a week calendar running from 7:00 AM to 7:00 PM, headed with the man's own name and seven dated columns, with its own ‹ Today › and its own Day · Week · Month · List · Year switches — five views where the Planning page offers five of its own, and note that this one carries Year and no Timeline. Before you have placed anything it says:
No slots to schedule yet — click the calendar to add a time slot.
Lay the blocks
Click a day and an eight-hour block appears. As blocks go down, the summary line keeps count of what is left to lay.
Save, and it appears
History, Cancel and Save finish the dialog, and they are the only three buttons on it besides the calendar's own. There is no typed date anywhere — counted on the running dialog, it carries no input box at all, so the calendar is the only way to say when. Once you save, the holder's line in the estimate stops saying Not scheduled and names the span instead, and the work appears on the Planning page.
The five views
All five show the same schedule. They differ in how much time they put on screen and whether your people get a row each.
Timeline
Timeline is the only view with a lane per person. Down the left is every worker in alphabetical order, then every crew. On the company walked here that was sixteen lanes — fourteen workers and two crews (Finishing Crew and Framing Crew), and no subcontractor lane, because nothing on these jobs was delegated at the time. The grid is a week wide at hour resolution, which is far wider than the screen, so you see roughly a day at a time and scroll sideways for the rest. This is the view for who is on what.
Week
Week puts seven days across the screen with no lanes — everybody's bars share the same columns, dated column heads across the top and the hours from 7:00 AM to 7:00 PM down the left.
Day
Day is one day.
Month
Month is the ordinary month grid and it is the view that shows the most work at once. If you want to find where a job's time actually sits, start here: one press of ‹ from today reached a month carrying sixteen bars on the walk, where the other four views had shown none.
List
List shows only the days that have something on them, as dated rows. A period with no work gives a list carrying the words No events — which is a real answer, not a failure.
Moving around the calendar
› moves forward, ‹ back, Today returns. How far one press moves, and what the read-out beside them does about it, depends on the view. Every row below was driven — the read-out taken before the press and again after it:
| view | one press of › moves | the read-out before → after |
|---|---|---|
| Day | one day | September 6, 2026 → September 7, 2026 |
| Week | one week | September 6 – 12, 2026 → September 13 – 19, 2026 |
| Timeline | one week, the same as Week | September 6 – 12, 2026 → September 13 – 19, 2026 |
| Month | thirty days | September 2026 → October 2026 |
| List | thirty days | September 2026 → October 2026 |
Day
one press of › moves
one day
the read-out before → after
September 6, 2026 → September 7, 2026
Week
one press of › moves
one week
the read-out before → after
September 6 – 12, 2026 → September 13 – 19, 2026
Timeline
one press of › moves
one week, the same as Week
the read-out before → after
September 6 – 12, 2026 → September 13 – 19, 2026
Month
one press of › moves
thirty days
the read-out before → after
September 2026 → October 2026
List
one press of › moves
thirty days
the read-out before → after
September 2026 → October 2026
What the read-out names
The read-out names the period you are looking at, and it names exactly as much of it as is true. In Day that is the whole day. In Week and Timeline it is both ends of the week drawn, so a week that runs out of one month into the next names both — August 30 – September 5, 2026. It changes on every press, which is how you can tell at a glance that the arrow did something.
The worker's seat answers alike
The worker's own seat answers by the same rule (Chapter 21). Both pages carry the same three controls over the same kind of calendar, and they give the same answer to what period am I looking at, so a builder telling a man over the telephone which day to open is describing the same line on both screens.
Reading the bars
A bar's text depends on the view, because the lane already tells you some of it.
In Month, Week, Day and List a bar names the person, the work and the hours:
Frank Adams · Timber-frame structural wall (timber-frame house) · 8h
In Timeline the name is dropped
In Timeline the person's name is dropped — his lane already carries it — and the bar names the work and the project instead.
Whole days and short days
Whole working days read 8h. Short days are printed as they are: 0.16h and 1.8h both appeared on the job walked here, and those are real figures, not rounding faults — the last block of a share is however many hours are left over.
Delegated work looks different
Delegated work looks different on purpose. A work you have given to a subcontractor rides its own lane, in its own colour, with an arrow and the subcontractor's name instead of hours:
↗ Reinforced concrete foundation slab · [the subcontractor]
You get no per-person detail inside it, which is correct: how the subcontractor splits the job between their own people is their business, not yours.
This chapter does not picture delegated work.
Clicking a bar
Any bar opens a small read-only panel. There are two shapes.
For your own people
For your own people, it names the work and the project, then the person, and then:
Project DrawToBid funny home Dates Mon, Jul 20 – Tue, Aug 4 Share 25% share Status Not started Work's overall progress — Finished 0% · Underway 0% · Not started 100%
What Share means
Share is how much of the work this person is responsible for — not how much of it they have done. The progress bar underneath is labelled Work's overall progress because it is about the whole work, everybody on it included, not about the person named above it.
For delegated work
For delegated work, the person and share are replaced by the subcontractor:
Delegated to [the subcontractor] Delegated Whole work
Open in project
At the bottom of both is Open in project ↗, which takes you to the project the bar belongs to.
Status tells the truth about time
Status tells the truth about time. A work whose start day has not arrived reads Not started even if it is fully scheduled — it will not claim to be in progress just because somebody put dates on it.
When work runs late
A work whose last scheduled day has passed while the work is still open is drawn with a dashed red border, on every one of its bars.
The limits of the marker
That is the whole mechanism, and it is worth understanding its limits, because it is easy to expect more from it:
It is passive. Nothing is sent, nobody is told, and there is no list of late work anywhere on this page. The bar simply looks different, and you have to be looking at it.
It is about dates, not effort — it fires because the days have gone by and the work has not been closed out, not because anyone measured how far behind you are.
It applies to every bar of that work at once, including days that went perfectly.
On the job walked here
On the job walked here every bar carried it — all thirty-six of them, across July and August, because all of that work was scheduled in the past and none of it had been closed out. That is the signal working correctly, and it is also a fair warning about how it will read on a real job: a mark that appears on everything tells you nothing about which thing to chase. Treat it as a reminder to close work out as it finishes, not as a list of what is behind.
One person booked twice
This is the question most people bring to a planning page, and the answer is a plain one.
DrawToBid shows you the clash and leaves the decision to you. It does not check, refuse, or warn.
Two different people working the same day is normal and needs no comment — that is just a crew. But one person booked twice on the same day is not normal, and it is worth knowing exactly what the product does about it, which was tested directly.
A labourer was already working eight-hour days on one work across a three-week span. A second work he also held had no dates on it. His scheduler was opened for that second work, walked back with the ‹ arrow to the days he was already fully booked, and given three more eight-hour blocks squarely on top.
His other work, hatched
His other work is drawn on that calendar, hatched. Each block he already carries appears in grey diagonal hatching in his lane, on the day it falls, labelled with the work, the project and the hours — Timber-frame structural wall (timber-frame house) · DrawToBid funny home · 8h. A line above the calendar says what they are:
The hatched blocks are work Frank Adams (general builder) is already booked on. They belong to other assignments — you can't edit them here, and you can still schedule over them.
Two things about that line
Two things about that line are worth knowing before you rely on it:
It is about the man, not about the week you are looking at. It appears whenever he carries other work at all, so you can be reading it on a week where none of his hatched blocks fall. Walk the arrows until you can see the days you care about, and count bars rather than trusting the sentence on its own.
The hatched blocks are read-only here. They have no drag handles: you can see what he is committed to, and you cannot move it from this dialog. To change it, open the scheduler for that work.
Nothing objects
Beyond drawing them, nothing objects:
No warning, no refusal, and nothing marked. No block turns red, nothing says double-booked, and the hatched blocks and the ones you are laying look equally ordinary side by side. The running total counts hours against this work's target only — 2.8h to schedule — your 25% share of 11.3h — which is the one thing it measures. Pile more onto the day than this work needs and it will say so, but only about this work: it read · 8h over once the day held two eight-hour blocks, counting the overshoot against this work's own 11.3h. It knows nothing about the eight hours he is already giving somebody else that day.
It saves without complaint.
The Planning page then shows both. In his lane, on the same days, sit his blocks for the first work and his blocks for the second. Neither is marked in any way.
So a man can be booked sixteen hours in one day, and the product will let you do it deliberately — with his other work in front of you while you do.
What this means in practice
What this means in practice: the scheduler now tells you enough to catch this yourself, so walk it back over the days you are about to fill and look at what is already hatched there before you save. The Planning page is still the wider view — the Timeline gives each person a lane of their own and shows every job at once — but you no longer have to leave the dialog to find out whether the man is spoken for. Nothing in the product is watching on your behalf; both screens simply show you, and the judgement stays yours.
Who can open this page
The owner sees everything described above.
The foreman
A foreman reaches the same page and gets the same ten controls — three arrows, five views and both filters — the same lanes and the same bars. Planning is not one of the pages a foreman is kept out of.
No money on it either way
And there is no money on it for him to be kept from. That is worth stating plainly, because a foreman is kept away from the job's money everywhere else in the product. Every $-shaped reading on this page was collected, on the owner's screen and on the foreman's, and both came back empty. This page is about hours and days; it never prices them. So the rule that a foreman sees no project money is not being bent here — there is simply nothing of the kind on the page for either of them.
An invited worker
A worker invited to one of the company's projects does not get this page — and he is not refused either. Typing the Planning address sends him instead to the company's Shared projects landing, headed with the company's name and his WORKER badge:
Shared projects Projects [your company] has shared with you. Open one to view it in your scoped workspace. DrawToBid funny home — Open
That is the right answer for him and it is worth knowing the shape of it: he is not told he lacks access to a page, he is handed the one thing on this workspace that is his. Chapter 21 is his seat.
Somebody who holds nothing here
Somebody who holds nothing in this company at all — no membership and no project grant — gets the flat refusal instead:
No access to this company You don't have an active invitation to this company workspace. Back to editor
Back to editor is the way out, and it leads to their own editor, not to yours.
A person with no company
A person with no company at all never arrives here in the first place. An account registered through the product's own form, verified and signed in for the first time, lands on its own empty editor — Untitled project, 0 elements, with File, Save, Share and Calculate all present because inside their own workspace they are the owner. Your company's addresses are not part of their product. Chapter 36 is that person's chapter.
Does the plan reach the people in it?
Not through this page, and not through anything found beside it.
Two schedules were laid and saved during this walk. Afterwards the general contractor's own notification bell held only the items that were already there — price approvals and a customer's approval — and nothing at all about either schedule.
The worker is told he has been given a WORK, and that is a different thing from being told his DAYS. Chapter 21 drives the notification bell on his own seat: a work handed to him puts a line on it within the minute — "You were assigned a work" — naming the project. Nothing equivalent was found for the schedule itself, on either side.
What can be said plainly: laying a schedule is not an announcement. If a plan needs to reach the people in it, that is still done the way it was always done — by telling them.
What this chapter did not cover
Named so their absence is not read as everything being covered:
what a customer or a subcontractor sees of the Planning page, if anything — the owner, the foreman, an invited worker and an account with no company at all were tried;
the schedule History panel, which the scheduling dialog offers beside its Save;
clearing a schedule once it is laid, and what the page shows afterwards;
whether a schedule laid by the built-in assistant behaves differently from one laid by hand — the page is built to refresh itself when that happens, and that path was not exercised;
anything about the order work must happen in. There are no dependencies between works in DrawToBid, nothing here knows that walls come before paint, and this page will let you schedule them in any order you like.